Gantt view
The Gantt view lays your tasks out on a timeline. Drag bars to change dates, and link tasks so you can see what waits on what.

01Open the Gantt#
Click Gantt in the view bar. Task names sit on the left and their bars on the right. Weeks start on Sunday; to change that, open View settings and pick a Week start (Monday, Saturday or Sunday).
02Change dates#
- Move a task: drag its bar. The length stays the same.
- Change the start or due date: drag the left or right edge of the bar.
- Date a task that has none: drag across its row.
03Link tasks#
Press D to start linking, then connect one bar to another. Press Esc when you are done.
04Zoom and Today#
The zoom buttons step from single days up close out to whole years, a little at a time, and the bar between them shows how far in you are. Auto fit fits all your dated tasks on screen. Today scrolls back to the current date, which is marked on the timeline.
05Group the timeline#
The controls at the top left group the timeline, for example by project or by person, the same way as swim lanes.