The Gantt view lays your tasks out on a timeline. Drag bars to change dates, and link tasks so you can see what waits on what.

01Open the Gantt#
Click Gantt in the view bar. Task names sit on the left and their bars on the right. Weeks start on Monday.
02Change dates#
- Move a task: drag its bar. The length stays the same.
- Change the start or due date: drag the left or right edge of the bar.
- Date a task that has none: drag across its row.
03Link tasks#
Press D to start linking, then connect one bar to another. Press Esc when you are done.
04Zoom and Today#
The zoom buttons go from days up close to months at a glance, seven steps in all. Today scrolls back to the current date, which is marked on the timeline.
05Group the timeline#
The controls at the top left group the timeline, for example by project or by person, the same way as swim lanes.